A new wash plant, built while the quarry kept producing.
Power, motor control and PLC automation for a new sand wash plant, delivered as design and construct.

The brief
A new plant, and a quarry that couldn't stop.
A new kiosk and supply, motor control for every pump, screen and conveyor, and a PLC system tied back to the existing control room. The quarry had to keep supplying customers throughout.
We delivered the full electrical and control package as design and construct, from the new supply through to drives, PLC, HMI and commissioning. Some critical equipment came from Europe on long lead times, so the plant had to run reliably from day one without the quarry's customers ever going short.
Scope of works
- New kiosk and supply, including the cut-over from the old supply to the larger one
- Main switchboard, two motor control centres and a dedicated slurry drive cabinet
- Variable speed drives on every motor
- PLC and HMI control system, linked back to the existing control room
- Flow meters and instrumentation across the process
- Commissioning on water first, then on sand, before handover to production

The Full Circuit Method
Four stages, on a quarry that kept supplying throughout.
01 Understand the job completely
We wired Dandy's original sand plant in 2014, so we already knew the site, the plant and the control room. The site walk focused on how the new plant would tie in, and how to cut over without stopping production longer than necessary.
02 Price it honestly
Dandy engaged us directly as a long-standing client. We delivered it as design and construct, with the detailed electrical design done by our specialist design partner and managed by us.
03 Own every part of it
Around 3,400 labour hours over eleven months, built while the existing plant kept running. Every shutdown was notified well ahead so Dandy could stockpile enough sand to keep customers supplied. When the European flow meters went on back order, we sequenced the rest of the install around them.
04 Stay connected
Three years of control system support since: PLC changes and a blending program, bore and dam pump control, CCTV across the site, and a site power pole replacement.

Outcome
A new sand wash plant commissioned and handed over in 2023, with the quarry producing the whole way through. More than ten years and two sand plants on, we're still the quarry's electrical and controls contractor.
Dandy Premix Quarries, Grantville. A client since 2013.